AETE Concept Review
Thursday, February 22, 2018 -
8:15 AM
Monday, February 19, 2018
Tuesday, February 20, 2018
Wednesday, February 21, 2018
Thursday, February 22, 2018
8:15 AM
Closed Session
Closed Session
8:15 AM - 8:30 AM
8:30 AM
Design approach, org chart and review status
-
Alexander Gottberg
(
TRIUMF
)
Design approach, org chart and review status
Alexander Gottberg
(
TRIUMF
)
8:30 AM - 8:50 AM
8:50 AM
Design inputs, requirements and end-use
-
Tom Day Goodacre
(
TRIUMF
)
Design inputs, requirements and end-use
Tom Day Goodacre
(
TRIUMF
)
8:50 AM - 9:20 AM
9:20 AM
Design concept - 3D models - status of key interfaces
-
Alexander Gottberg
(
TRIUMF
)
Design concept - 3D models - status of key interfaces
Alexander Gottberg
(
TRIUMF
)
9:20 AM - 10:20 AM
Room: MOB Conf Rm
10:20 AM
Coffee Break
Coffee Break
10:20 AM - 10:40 AM
10:40 AM
Top risks and mitigating actions - development test centers and test results
-
Kevin Chen
(
TRIUMF
)
Top risks and mitigating actions - development test centers and test results
Kevin Chen
(
TRIUMF
)
10:40 AM - 11:20 AM
Room: MOB Conf Rm
11:20 AM
Compliance matrix - compare against requirements
-
Tom Day Goodacre
(
TRIUMF
)
Compliance matrix - compare against requirements
Tom Day Goodacre
(
TRIUMF
)
11:20 AM - 11:40 AM
11:40 AM
Present cost-estimates
-
Norman Muller
(
TRIUMF
)
Present cost-estimates
Norman Muller
(
TRIUMF
)
11:40 AM - 12:10 PM
Room: MOB Conf Rm
12:10 PM
Present schedule, critical path and key dependencies
-
Alexander Gottberg
(
TRIUMF
)
Present schedule, critical path and key dependencies
Alexander Gottberg
(
TRIUMF
)
12:10 PM - 12:30 PM